Adani Transmission to acquire Warora-Kurnool Transmission for Rs 3,370 cr




Limited (ATL) on Saturday said it has signed an agreement with Essel Infraprojects Limited (EIL) for the acquisition of Warora-Kurnool Transmission Limited (WKTL) for about Rs 3,370 crore.


Adani Transmission, India’s largest private sector power transmission and retail distribution company, said the acquisition is valued at a target of Rs 3,370 crore.



“The regulatory approval for substitution of original awardee in the contract by ATL has already been received from Central Electricity Regulatory Commission,” the company said in an exchange filing.


“The lenders consent and other necessary regulatory approvals shall be obtained before closure of transaction,” it said


With this acquisition, the cumulative network of ATL will reach 17,200 ckt km, out of which 12,350 ckt km is already operational and 4,850 ckt km (including this asset) is in various stages of execution.


With this enhanced scale of operations, ATL will enjoy substantial benefits in terms of cost optimisation and shared resources and will also fortify its position of being the largest private sector transmission company in the country, the company said


Commenting om the development, Anil Sardana, MD and CEO of said: “The acquisition of WKTL will bolster ATL’s pan-India presence, consolidating further its position as the largest private sector transmission company in India. This strategic West to South 765 KV interconnector with Substation in Southern India, completes ATL presence in all regions of the country.”


“This asset will not only increase ATL’s size and scale but will also take ATL closer to its target of setting up 20,000 ckt km of transmission lines by 2022. The acquisition is a further demonstration of ATL’s drive towards differentiated capability through inorganic growth, successful integration and making such assets value accretive, for long term sustainable value creation for its stakeholders,” Sardana said.


Warora-Kurnool Transmission will develop, operate and maintain transmission lines aggregating to 1,750 ckt km. The 765 kV inter-state transmission line links Warora– Warangal and Chilakaluripeta-Hyderabad–Kurnool with a 765/400 kV new sub-station at Warangal.

Dear Reader,

Business Standard has always strived hard to provide up-to-date information and commentary on developments that are of interest to you and have wider political and economic implications for the country and the world. Your encouragement and constant feedback on how to improve our offering have only made our resolve and commitment to these ideals stronger. Even during these difficult times arising out of Covid-19, we continue to remain committed to keeping you informed and updated with credible news, authoritative views and incisive commentary on topical issues of relevance.

We, however, have a request.

As we battle the economic impact of the pandemic, we need your support even more, so that we can continue to offer you more quality content. Our subscription model has seen an encouraging response from many of you, who have subscribed to our online content. More subscription to our online content can only help us achieve the goals of offering you even better and more relevant content. We believe in free, fair and credible journalism. Your support through more subscriptions can help us practise the journalism to which we are committed.

Support quality journalism and subscribe to Business Standard.

Digital Editor





Source link

Leave a Reply

Your email address will not be published. Required fields are marked *